GREENWOOD, Ind.— Johnson County officials met with the Indiana Department of Transportation Monday to discuss the details of a $1.2 million project to rehab Madison Avenue’s bridge over Pleasant Run Creek.
The bridge is located east of Greenwood Park Mall between County Line Road and Fry Road.
Crews will begin demolishing the bridge and then replace it beginning in March. The completion date is scheduled for September 30.
The project includes new bridge rails, sidewalks and street approaches.
INDOT officials say traffic will be shifted to the west side of the bridge—vacating lanes on the east side for demolition and reconstruction. Phase II construction moves to the west side—shifting traffic to the east side of the bridge.
The Federal Highway Administration is funding 80 percent of the project. Johnson County will pay 20 percent of the costs.